Current and Future Projects (Physical Plant and Others) - Master List

PROJECT TITLE DISCRIPTION ESTIMATED BUDGET PROJECTED START PROJECTED END STATUS FUNDING SOURCE
Hughes Hall Dressing Rooms & Showers Convert gang showers to private showers with dressing rooms $140,000 May-13 August 2013 Planning Plant Fund
HPER Expansion Phase III addition, racquet ball courts, weight room, natatorium, & offices $15,500,000 July 2013 October 2014 Construction Document Planning Bonds
Stone Dam Creek Path Bike and walking trail, outdoor classroom $314,875 October 2012 Feb-13 Construction Grant $230,000 and Capital Reserves $84,875
ADEM Redundant Data Center Back up data center, new floor covering and paint $1,500,000 July 2013 March 2013 In progress Capital Reserves
North Overflow Parking Lot, Augusta St. Parking lot addition, appx. 152 spaces $430,000 April 2013 August 2013 CD’s Planning Access & Security, Deferred Maintenance
Bear Hall Parking Lot Minton site, 30 spaces low impact parking lot, bio-swells, crushed granite spaces, shuttle stop with shelter $80,000 May 2013 August 2013 CD’s Planning ?????
Dee Brown Garden Teaching garden, concrete paths, plant beds, raised HC beds $45,000 May 2013 August 2013 Planning $25,000 Cash & $20,000 In Kind
Farris Center Roofing replacement $625,000 May 2013 August 2013 Planning Deferred Maintenance
Mashburn Hall Lighting replacement with new fixtures and energy efficient T-12 fluorescent tubes & electronic ballasts. $50,000 September 2013 August 2013 In progress Deferred Maintenance
McAlister Hall District Cooling Connection Add McAlister to district chilled loop. $45,000 May 2013 August 2013 Planning Deferred Maintenance
Old Main Restrooms 1st Floor Convert offices to restrooms, add HC ramp into auditorium $302,000 March 2013 August 2013 Out for Bid Grant $152,000 & Capital Reserves $150,000
Physical Plant Storage Area Construct 2 storage buildings, fence in area for secure outdoor storage, add coiling door for access from physical plant compound to new area. $120,000 October 2012 June 2013 In progress Deferred Maintenance
Student’s Sports Field New soccer/football field for student use $390,000 March 2013 August 2013 Out for Bid SGA $50,000, Farris Fields R & R $50,000, Unallocated Deferred Maintenance $290,000
Burdick Hall Make Up Air Unit Install new make up fresh air unit $75,000 August 2012 December 2013 Complete Deferred Maintenance
Baridon Hall Boilers Replace domestic hot water tank with nine 105 gal. fiberglass tanks to increase energy efficiency $75,000 September 2012 December 2013 Complete Housing Deferred Maintenance
Torreyson Library Academic Success Center Convert microfiche room to computer study lab $25,000 September 2012 December 2013 Complete ???
Farris Center Boiler Rebuild Depot level clean and rebuild main building boiler $15,000 January 2013 March 2013 Parts ordered Building Maintenance
Arkansas Hall Corridor FCU’s Install new fan coil units in corridors $43,500 December 2012 March 2013 In progress Plant Fund
Stadium Park Apartments Renovate certain buildings $122,000 May 2013 August 2013 Planning Plant Fund
Hughes Hall Fire Sprinkler System Add fire sprinkler system $153,000 May 2013 August 2013 Planning Plant Fund
Baridon Hall Kitchen Add common kitchen $30,000 July 2013 August 2013 Planning Plant Fund
Farris Hall Kitchen Add common kitchen $25,000 July 2013 August 2013 Planning Plant Fund
New Hall Kitchen Add common kitchen $20,000 May 2013 June 2013 Planning Plant Fund
Conway Hall Dressing Rooms & Showers Convert gang showers to private showers with dressing rooms $135,000 June 2013 July 2013 Planning Plant Fund
Bernard Hall Dressing Rooms & Showers Convert gang showers to private showers with dressing rooms $148,000 July 2013 August 2013 Planning Plant Fund

 

This file "uca_projects_2013.csv" was last modified at 2013-02-19 14:58:21 by brentp.